Project Updates
2013-2014 Construction Updates

Parking Lot at B/North High
Gleeson Asphalt was the contractor on this project.  The project has been completed.

Lincoln/8th Street
Gleeson Asphalt was the contractor on Lincoln Avenue/8th Street.  Lincoln Avenue/8th Street has been substantially completed.   Due to the hot weather spell we are waiting for the grass to establish.  The project has been completed.

Juanita Place
Hank’s Excavating is the contractor on this project.  This project is 80% complete.  Sidewalks/curbs have been removed and re-poured.  The trees will be installed in November after they go dormant.  Lighting will be installed in November.  The asphalt will be laid before the end of October 2013.  The project has been completed.

Signal Hill Trail
Gleeson Asphalt will start construction the week of October 14, 2013.  This project should be completed by the end of 2013, weather dependent.

West Belleville Trail
Widman Construction will start construction October 10, 2013.  This project should be completed June 2014.

McClintock Avenue
Starting Monday, November 25, 2013 the water company will be replacing their water main from Mascoutah to Forest.  This work should take two to three weeks, weather dependent.  Gleeson will resume their storm sewer work once the water company finishes their work.

Phase I detours will be utilizing McKinley and Douglas Avenue as shown on the detour map.